Groundbreaking: Sunday, July 31, 2011
Estimated Completion Date: May 2012
Size: 18,000 square feet

Construction Project Schedule

November 2011 Sitework and grading completed

December 2011 Building Slab completed. Begin curbing and paving

February 2012 Rough Exterior Completed

April 2012 Painting, Millwork, and Flooring Completed

May 2012 Building completed and occupancy